MVC Construction

Project Details

Permit Number: 23-640

General Contractor: Grant Excavation LLC 

Jared Grant 517-643-2100 or Jared@grantexcavation.com

  • In this section, we will provide up-to-date scheduling of your project so you can see the status in real-time 24 hours a day.

  • In this section, we will post essential questions that need the owner's approval, such as change orders, product options, and selection.

  • In this section, our team posts photos and descriptions of the progress of the project. This is a space for you to check in and ask questions as they arise.

  • Materials & Labors Invoices Will Be Uploaded Bi-Weekly To Keep Everything On Track.

  • All plans, permits & contracts will live in this section for you to access with a single click.

Building Specifications

Building Manufacturer:

Dimensions 200’ x 150' (Gabled Roof)

Base building cost: $795,582

Items Included In The Price Above

- Complete structural steel package 

- All hardware needed to erect

- Framed openings 

- R-Panel wall cladding (26 gauge) Standing seam roof system - 10 Year Additional Warranty 

- R-Panel wall cladding (26 gauge)

- Eave and rake extensions (4'-0")  (Increased 2ft)

- 103 MPH wind load 

- 42.7 PSF roof snow load 

- (3) Stamped and sealed structural plans 

- Delivery to the job site

- Current lead time 10-16 weeks

- Color (TBD)

- Insulation (R-30 roof, R-19 walls)

Forecasted Building Cost:

Building Permit: $15,750

Utility Engineering: $2,500

Site Plan & City Legal Fees: $2,500

Foundation Engineering: $3,000

Site and Concrete Survey: $5,500

The Structure: $795,582

Excavation: $80,000

- Site Takeoff

- Utility Excavation & Daylighting

- Site Backfill & Concrete Preparation 

- Excess Material Disposal & Trucking 

*This number will vary depending on traditional concrete forming or Post Tension Forming. 

Building Erection: $338,000

- Super Structure

- All Trims & Sheeting 

- Window & Mandoor Install

- Insulation, Siding, Roofing & Trim 

Concrete: $405,000 (Looking into more cost effective options)

- For this project, there is a large amount of concrete, based on current forming techniques we will be in the 400K range.  However, I am looking into monolithic post tension concrete pour that would cut labor in half. 

Garage Doors w/ Glass: $21,000

- Eleven 14 ft x 18 ft panel doors

- Industrial Opener

- Install  

Mandoors: $9,500

- Four Man Doors w/ 24”x64” Wire Grid Windows 

Windows: $15,530

- Twenty 2 ft x10 ft Amsco Windows

Electrical: $180,000

- Power Connect 

- Panel Install 

- Shop & Office Lighting 

- Shop & Office Outlets 

- Exterior Lighting

- Power To Fans, Lighting, Swamp Coolers

- Fire Alarms 

*Specialty Electrical Not Yet Defined & Included In This Agreement

Fire Suppression: $65,000

- Delta Fire Suppression System 

- Fire Alarm system

Shop Heaters: $22,000

- 4 Modine Hearts Gas or Electric 

Shop Fans: $36,000

- Eight Big Ass Fans 14’ Footers 

Plumbing: $148,000

- Oil Trap

- Culinary Water & Sewer Tie-in

- Bathrooms & Kitchen Plumbing 

- Shop Sinks

- Pressure Washer Bay

- Water Spigots x 8

- Swamp Coolers

Two Bathroom Rooms: $38,000

-Bathroom 

-Fan Install

-Lumber & Drywall 

-Toilets 

-Sinks & Sink Fixtures 

-Wall Splashes

-Wash Basin

-Shower 

-Lighting 

-Labor

-ADA compliance

Employee Kitchen: $20,900

-Cabinets 

-Sink & Sink Fixtures

-Countertops

-Backsplash

-Lighting

-Lumber and Drywall

Two Offices: $46,600 

-Lumber & Drywall

-Labor

-Flooring

-Doors & Windows

Miller Paving $3.40/sqft: 16,000 sq ft of apron & parking: $54,400

Two Upper Apartments: $

-Heber City Fire Hazard

-Fire Blocking Door

-Kitchen

-Cabinets

-Sink

-Sink Fixtures

-Blacksplash

-Lighting

-Lumber & Drywall

-Labor

Budget

Forecasted Building Cost: 

Down Payment Required For Manufacture & Erector: $98,780.00

Enclosed Building Total: $477,084

Utilities: Power Upgrade & Basic Water Installation

Power Upgrade: $65,000

Basic Water Installation: $8,500

Shop Heater: $5,500

Utility Total: $79,000  

General Contracting Fees 10% + $125 Hourly Organizational Fees

Estimated Grand Total: $622,073.58

*Estimate Updated 9/25/2023 (Building Sales Tax)